DPS/HRPU/NFC/PT/TPT/CAP/11055 |
|
02/12/2019 |
|
27/01/2020 14:00:00 |
|
27/01/2020 14:00:00 |
|
27/01/2020 14:01:00 |
|
NA |
|
Rs. 430152 |
|
|
Qualifying Requirement : |
NOTE:
1. Bidders are advised to quote strictly in compliance with the instructions given in the header of the price bid template & NIT failing which the offer will be rejected.
2. All the vendors registered under MSE are to provide a declaration that they have registered their Udyog Aadhar Memorandum Number (UAM) on Central Public Procurement Portal (CPPP), failing which they cannot avail the benefit available to MSEs as contained in the Public Procurement Policy for MSEs order 2012 issued by MSME.
|
Sr. no | Item Category | Item Description | Qty | 1 | CAP | DESIGN, FABRICATION, TESTING,
SUPPLY, ERECTION, COMMISSIONING AND PERFORMANCE DEMONSTRATION, TRAINING
OF RESISTANCE HEATING FURNACE
ALONG WITH AUXILIARIES
| 2 | 2 | CAP | KANTHAL A-1 HEATING ELEMENTS
EMBEDDED IN FIBROTHAL MODULES OF
EACH TYPE.
(1 SET CONSIST OF 1 HEATING ELEMENT
AND IT.S FIBROTHAL MODULE. HOWEVER
IN 1 ELEMENT IF MORE THAN 1
FIBROTHAL MODULES ARE USED, SAME
SHALL BE SUPPLIED AS ONE SET.
SIMILARLY, IF 1 FIBROTHAL MODULE
CONSIST OF MORE THAN 1 ELEMENT,
SAME SHALL BE SUPPLIED AS 1 SET.)
| 4 | 3 | CAP | LIMIT SWITCHES, 2 NOS EACH TYPE
| 2 | 4 | CAP | ELECTRICAL SWITCHGEAR SUCH AS MCCB,
CONTACTORS, SOLENOID VALVES,
THERMAL OVERLOAD RELAYS, FUSES ETC.
USED IN THE SYSTEM, 1 NO EACH
| 2 | 5 | CAP | AC POWER CONTROLLER
| 2 | 6 | CAP | SEMICONDUCTOR FUSES OF AC POWER
CONTROLLERS (100% OF TOTAL
INSTALLED QUANTITY)
| 2 | 7 | CAP | PID CONTROLLER
| 2 | 8 | CAP | OTC
| 2 | 9 | CAP | 3 NOS OF DUPLEX THERMOCOUPLES
| 2 | 10 | CAP | C&F CHARGES | 1 | | | | |
| |
|
At Our Stores, NFC - KOTA, RAWATBHATA, RAJASTHAN |
|